Most pricing problems aren’t about being too expensive. They’re about not knowing your real costs, so you either guess high and lose the job or guess low and lose money doing it.
A good price is built in three layers: direct costs, overhead, and profit. Get each one right and the number takes care of itself.
Start with direct costs
Direct costs are everything you spend because this job exists: labour (at your loaded rate, not the wage), materials with a waste allowance, subcontractors, rentals, permits and disposal. Be honest about time. Include setup, travel, cleanup and the walkthrough at the end.
Recover your overhead
Overhead is what it costs to keep the doors open whether you work or not: insurance, vehicles, office, phones, software, accounting, marketing and your own admin time. Add up last year’s overhead and divide it by last year’s direct costs to get your overhead rate.
$120,000 overhead ÷ $600,000 direct costs = 20%. Every job needs to add 20% on top of its direct costs just to break even.
Add profit on purpose
Profit isn’t what’s left over. It’s a line you plan for. It pays for slow months, new equipment, mistakes and growth. Many contractors aim for a net profit of 10% or more after overhead, but decide on a target and price to it every time.
Markup vs margin
This is where good contractors lose money without realizing it. Markup is a percentage of your cost. Margin is a percentage of your price. They are not the same number.
If a job costs $10,000 and you mark it up 20%, you charge $12,000. But your margin is only $2,000 ÷ $12,000, or 16.7%. If you wanted a 20% margin, you needed to charge $12,500.
| Markup | Margin it gives you |
|---|---|
| 10% | 9.1% |
| 20% | 16.7% |
| 25% | 20% |
| 33% | 25% |
| 50% | 33.3% |
| 100% | 50% |
To hit a target margin, divide your cost by one minus the margin: price = cost ÷ (1 − margin). For a 25% margin on $10,000, that’s $10,000 ÷ 0.75 = $13,333. Our free contractor markup calculator does this both ways and shows markup and margin side by side.
A worked example
Loaded labour $5,200, materials $3,600, dumpster and permit $1,200.
Your 20% overhead rate adds $2,000. This is your break-even price.
For a 10% net profit, $12,000 ÷ 0.90 = $13,333. That’s a 25% gross margin.
Then check the market
Once you know your number, compare it to what the market will bear. If you’re well above competitors, look for waste in your costs or overhead before you cut profit. If you’re well below, you’ve been leaving money on the table. Either way, you’re deciding with real numbers instead of a gut feeling.