Contractor payment terms are the rules in your quote or contract that say how much the customer pays, when each payment is due, how they can pay and what happens if they’re late. For most residential service work, use “due on receipt” and collect before you leave. For projects over a few thousand dollars, take a deposit on signing, bill progress payments at clear milestones, and keep the final payment small. Save net 30 for commercial customers whose accounts payable process demands it.
Below: how to choose a due date, payment schedules for small, medium and large jobs, a worked example, how late fees work, and a payment clause to copy. Rules on deposits, late interest and holdbacks vary by province and state, so this is general guidance, not legal advice.
What are contractor payment terms?
Good payment terms answer six questions before the job starts:
| Term | What it answers | Typical residential setting |
|---|---|---|
| Deposit | How much up front? | 10–50% depending on job size and materials |
| Schedule | When is the rest due? | Milestones you can see: rough-in, drywall, completion |
| Due date | How long after an invoice? | On receipt, or net 7 |
| Payment methods | How can they pay? | Card, e-Transfer/ACH, cheque |
| Late fee | What if they don’t pay? | Monthly interest or flat fee after a grace period |
| Change orders | How do extras get billed? | Signed before work, added to next invoice |
Put them on the quote, not just the invoice. A customer who signed the terms before work began is far easier to collect from than one seeing them for the first time on the final bill.
Due on receipt, net 7, net 15 or net 30?
| Term | Means | Use it for |
|---|---|---|
| Due on receipt | Pay when the invoice arrives | Service calls, small repairs, anything finished in a day |
| Net 7 | Pay within 7 days of the invoice date | Residential project milestones, repeat customers |
| Net 15 | Pay within 15 days | Property managers and small businesses |
| Net 30 | Pay within 30 days | Commercial clients, general contractors, institutions |
| Net 45 / 60 | Pay within 45 or 60 days | Large commercial work only, priced to cover the wait |
Pick the shortest term the customer can realistically meet. Every extra week of terms is a week you’re carrying payroll and materials on your own cash. If a commercial client insists on net 60, that cost belongs in your price.
Write that an invoice counts as received the day you email it. It closes off the “we never got it” delay.
Payment schedules by job size
Service calls and small repairs. Take payment on site by card or pay link before you pull out of the driveway. Ask for a deposit only if you’re ordering special parts.
About 30% on signing to cover materials and lock the date, balance due on completion. Example: a $9,000 bathroom refresh is $2,700 down, $6,300 at the end.
For example 25% on signing, 25% at rough-in, 35% at drywall or substantial completion, 15% at final walkthrough.
Monthly or milestone draws tied to work completed, with a small deposit. Common on new builds and large renovations, and often required by lenders.
How big should the deposit be? Our guide to how much deposit a contractor should ask for goes deeper, including provincial and state limits.
Worked example: a $38,000 basement
Here’s a basement finish priced at $38,000 plus tax, with four payments tied to milestones the homeowner can see for themselves:
| Milestone | % | Amount (before tax) | Due |
|---|---|---|---|
| Contract signed | 25% | $9,500 | On signing |
| Framing, electrical and plumbing rough-in passed inspection | 25% | $9,500 | Net 7 |
| Drywall taped and primed | 35% | $13,300 | Net 7 |
| Final walkthrough complete | 15% | $5,700 | On receipt |
| Total | 100% | $38,000 |
Why this works: materials and early labour are covered by the first two payments, you’re never more than one milestone of labour ahead of the customer, and the final 15% is big enough to motivate you to finish the punch list but small enough that a stalled final payment doesn’t sink your month. If the homeowner adds pot lights mid-job, the change order goes on the next milestone invoice.
Late fees and what you can charge
A late fee works only if it’s in the signed terms before the work starts. Common structures:
- Monthly interest: for example 1.5% per month on the overdue balance. Always state the annual rate too (18% per year); Canada’s federal Interest Act generally requires an annual rate to be stated.
- Flat fee: for example $35 after 15 days late. Simple, and easy to explain on small invoices.
- Grace period: a few days before any fee applies keeps goodwill with customers who are just slow.
Maximum rates and rules differ by province and state, so check yours. In practice, the fee is mostly a nudge; most of the value comes from polite, automatic reminders. If an invoice is already overdue, follow the steps in how to collect unpaid invoices.
Payment terms clause to copy
Paste this into your quote or contract and fill in the brackets. Have a local lawyer check your final version once.
PAYMENT TERMS Deposit: [30]% of the contract price ($[____]) is due on signing. Work is scheduled once the deposit is received. Progress payments: [40]% ($[____]) due when [rough-in / framing / tear-off] is complete. Balance ($[____]) due on substantial completion. Due date: Each invoice is due [on receipt / within 7 days of the invoice date]. An invoice is considered received on the day it is emailed to the address above. Accepted payment: credit/debit card, e-Transfer/ACH, or cheque. Late payment: Balances unpaid [15] days after the due date are charged [1.5]% per month ([18]% per year) on the overdue amount, or $[__], whichever is greater. [Check the maximum allowed in your province/state.] Change orders: Changes to the scope are priced in writing and signed before work starts. Approved change orders are added to the next progress invoice. Suspension: If a payment is more than [10] days late, we may pause work after written notice until the account is brought current. Holdback / retainage: [Where required by law, the statutory holdback is withheld and released according to that law.]
Commercial work: net 30, holdback and retainage
Commercial and GC work runs on different rules. Expect net 30 or longer, invoices that must match a purchase order exactly, and a percentage held back from each payment until the job is done.
| Canada | United States | |
|---|---|---|
| What it’s called | Holdback | Retainage |
| Typical amount | 10% in Ontario and many provinces, set by provincial construction or lien law | Often 5–10%, set by contract and some state laws |
| Released | After the lien period passes, per provincial rules | At completion or per contract |
| Prompt payment rules | Ontario and several other provinces have prompt payment legislation | Many states have prompt payment acts |
Check your province or state’s construction and lien legislation for exact percentages and deadlines. Price commercial jobs knowing that 10% of the money may arrive months after you finish.
Making the terms actually stick
Terms on paper don’t pay bills. Systems do. The contractors who get paid on time do the same four things every job:
- Get the terms signed with the quote, before any work.
- Collect the deposit the moment the customer says yes, not at the first site visit.
- Send each milestone invoice the day the milestone is hit, with a pay link.
- Let reminders go out automatically, so nobody has to make an awkward call.
Contruva does all four. Quotes carry your payment terms, get signed on the customer’s phone and collect the deposit on approval. Invoices include card and bank pay links through Stripe with no extra Contruva fee, automatic reminders, and late fees as a percent or flat amount with grace days and caps. More ideas in how to get paid faster as a contractor. Try it free for 7 days on our pricing page.