Contractor payment termsthat protect your cashand still win the job.

Your payment terms decide whether you’re financing your customers’ jobs or they are. Here’s which terms to use for which jobs, worked payment schedules, and a clause you can paste into your next quote.

Contractor payment terms are the rules in your quote or contract that say how much the customer pays, when each payment is due, how they can pay and what happens if they’re late. For most residential service work, use “due on receipt” and collect before you leave. For projects over a few thousand dollars, take a deposit on signing, bill progress payments at clear milestones, and keep the final payment small. Save net 30 for commercial customers whose accounts payable process demands it.

Below: how to choose a due date, payment schedules for small, medium and large jobs, a worked example, how late fees work, and a payment clause to copy. Rules on deposits, late interest and holdbacks vary by province and state, so this is general guidance, not legal advice.

What are contractor payment terms?

Good payment terms answer six questions before the job starts:

TermWhat it answersTypical residential setting
DepositHow much up front?10–50% depending on job size and materials
ScheduleWhen is the rest due?Milestones you can see: rough-in, drywall, completion
Due dateHow long after an invoice?On receipt, or net 7
Payment methodsHow can they pay?Card, e-Transfer/ACH, cheque
Late feeWhat if they don’t pay?Monthly interest or flat fee after a grace period
Change ordersHow do extras get billed?Signed before work, added to next invoice

Put them on the quote, not just the invoice. A customer who signed the terms before work began is far easier to collect from than one seeing them for the first time on the final bill.

Due on receipt, net 7, net 15 or net 30?

TermMeansUse it for
Due on receiptPay when the invoice arrivesService calls, small repairs, anything finished in a day
Net 7Pay within 7 days of the invoice dateResidential project milestones, repeat customers
Net 15Pay within 15 daysProperty managers and small businesses
Net 30Pay within 30 daysCommercial clients, general contractors, institutions
Net 45 / 60Pay within 45 or 60 daysLarge commercial work only, priced to cover the wait

Pick the shortest term the customer can realistically meet. Every extra week of terms is a week you’re carrying payroll and materials on your own cash. If a commercial client insists on net 60, that cost belongs in your price.

Define “received”

Write that an invoice counts as received the day you email it. It closes off the “we never got it” delay.

Payment schedules by job size

Under $2,500
Due on completion.

Service calls and small repairs. Take payment on site by card or pay link before you pull out of the driveway. Ask for a deposit only if you’re ordering special parts.

$2,500 to $15,000
Deposit + balance.

About 30% on signing to cover materials and lock the date, balance due on completion. Example: a $9,000 bathroom refresh is $2,700 down, $6,300 at the end.

$15,000 to $75,000
Deposit + progress + final.

For example 25% on signing, 25% at rough-in, 35% at drywall or substantial completion, 15% at final walkthrough.

Over $75,000
Draw schedule.

Monthly or milestone draws tied to work completed, with a small deposit. Common on new builds and large renovations, and often required by lenders.

How big should the deposit be? Our guide to how much deposit a contractor should ask for goes deeper, including provincial and state limits.

Worked example: a $38,000 basement

Here’s a basement finish priced at $38,000 plus tax, with four payments tied to milestones the homeowner can see for themselves:

Milestone%Amount (before tax)Due
Contract signed25%$9,500On signing
Framing, electrical and plumbing rough-in passed inspection25%$9,500Net 7
Drywall taped and primed35%$13,300Net 7
Final walkthrough complete15%$5,700On receipt
Total100%$38,000

Why this works: materials and early labour are covered by the first two payments, you’re never more than one milestone of labour ahead of the customer, and the final 15% is big enough to motivate you to finish the punch list but small enough that a stalled final payment doesn’t sink your month. If the homeowner adds pot lights mid-job, the change order goes on the next milestone invoice.

Late fees and what you can charge

A late fee works only if it’s in the signed terms before the work starts. Common structures:

  • Monthly interest: for example 1.5% per month on the overdue balance. Always state the annual rate too (18% per year); Canada’s federal Interest Act generally requires an annual rate to be stated.
  • Flat fee: for example $35 after 15 days late. Simple, and easy to explain on small invoices.
  • Grace period: a few days before any fee applies keeps goodwill with customers who are just slow.

Maximum rates and rules differ by province and state, so check yours. In practice, the fee is mostly a nudge; most of the value comes from polite, automatic reminders. If an invoice is already overdue, follow the steps in how to collect unpaid invoices.

Payment terms clause to copy

Paste this into your quote or contract and fill in the brackets. Have a local lawyer check your final version once.

PAYMENT TERMS

Deposit: [30]% of the contract price ($[____]) is due on signing.
Work is scheduled once the deposit is received.

Progress payments:
  [40]% ($[____]) due when [rough-in / framing / tear-off] is complete.
  Balance ($[____]) due on substantial completion.

Due date: Each invoice is due [on receipt / within 7 days of the
invoice date]. An invoice is considered received on the day it is
emailed to the address above.

Accepted payment: credit/debit card, e-Transfer/ACH, or cheque.

Late payment: Balances unpaid [15] days after the due date are charged
[1.5]% per month ([18]% per year) on the overdue amount, or $[__],
whichever is greater. [Check the maximum allowed in your province/state.]

Change orders: Changes to the scope are priced in writing and signed
before work starts. Approved change orders are added to the next
progress invoice.

Suspension: If a payment is more than [10] days late, we may pause work
after written notice until the account is brought current.

Holdback / retainage: [Where required by law, the statutory holdback is
withheld and released according to that law.]

Commercial work: net 30, holdback and retainage

Commercial and GC work runs on different rules. Expect net 30 or longer, invoices that must match a purchase order exactly, and a percentage held back from each payment until the job is done.

CanadaUnited States
What it’s calledHoldbackRetainage
Typical amount10% in Ontario and many provinces, set by provincial construction or lien lawOften 5–10%, set by contract and some state laws
ReleasedAfter the lien period passes, per provincial rulesAt completion or per contract
Prompt payment rulesOntario and several other provinces have prompt payment legislationMany states have prompt payment acts

Check your province or state’s construction and lien legislation for exact percentages and deadlines. Price commercial jobs knowing that 10% of the money may arrive months after you finish.

Making the terms actually stick

Terms on paper don’t pay bills. Systems do. The contractors who get paid on time do the same four things every job:

  • Get the terms signed with the quote, before any work.
  • Collect the deposit the moment the customer says yes, not at the first site visit.
  • Send each milestone invoice the day the milestone is hit, with a pay link.
  • Let reminders go out automatically, so nobody has to make an awkward call.

Contruva does all four. Quotes carry your payment terms, get signed on the customer’s phone and collect the deposit on approval. Invoices include card and bank pay links through Stripe with no extra Contruva fee, automatic reminders, and late fees as a percent or flat amount with grace days and caps. More ideas in how to get paid faster as a contractor. Try it free for 7 days on our pricing page.

01Questions

Straight answers.

Still unsure? Call us at +1 (647) 922-5436. A real person picks up.

Ask us anything

What are standard payment terms for contractors?

Residential service work is usually due on receipt. Residential projects use a deposit plus progress payments at milestones. Commercial work is usually net 30, often with a holdback or retainage.

What does net 30 mean for a contractor?

Net 30 means the customer has 30 days from the invoice date to pay in full. It’s common with commercial clients and general contractors.

How much deposit should a contractor take?

Many contractors take 10 to 50% depending on job size and materials, with 25 to 30% common on mid-size projects. Some provinces and states limit deposits on home improvement contracts, so check local rules.

Can a contractor charge a late fee?

Yes, if the late fee is in the terms the customer agreed to before work started. State it as a monthly and annual rate or a flat fee, and check your province or state’s maximum.

What is a progress payment?

A progress payment is a portion of the contract price billed when a defined stage of the job is complete, such as rough-in or drywall.

Should payment terms be on the quote or the invoice?

Both, but the quote matters most. Terms the customer signed before work starts are much easier to enforce.