How to pricea deck build,step by step.

A deck build prices by the square foot, and the material you choose moves the price more than anything else. Work out materials, labour, footings and permits separately, then add your margin.

Learning how to price a deck build starts with one number: the cost per square foot installed, which in Ontario in 2026 runs about $45 to $95 a square foot depending on the material. A pressure-treated deck is the cheapest, a composite deck costs 40% to 60% more, and the extras, stairs, railings, footings and permits, are where most estimates go wrong. The method below prices each part separately, so the quote is right even when the deck is not a simple rectangle.

Decks are one of the most quoted outdoor jobs in Canada, and one of the most underpriced. The wood is only part of the cost. Footings, framing, hardware, railings, stairs, disposal of the old deck, and the permit all sit on top of the boards, and a quote that misses them is a job that loses money. Our free deck calculator does the material maths for you, and the fence installation pricing guide uses the same per-foot method for the other common outdoor job. This is general pricing information, not tax or legal advice; confirm permit and tax rules with your local building department and the CRA.

What a deck build costs per square foot

All figures below are Canadian dollars, installed, including footings, framing and standard railing unless noted, from Ontario cost guides published in 2026. Use ranges, not single numbers, because lumber prices, site access and the town you are in all move the price.

MaterialCost per sq ft installedBest for
Pressure-treated lumber$35 to $65Budget builds, rental properties, simple decks
Cedar$55 to $105A natural look with more upkeep
Composite, mid-range$65 to $95Most family decks; low maintenance
PVC or capped polymer$80 to $130Wet areas, pool decks, premium builds
Premium composite in the GTA$90 to $160High-end Toronto builds with premium finishes

Overall, expect $45 to $95 a square foot for a typical Ontario deck. The low end is a simple pressure-treated deck on flat ground with easy access. The high end is composite with stairs, railings, lighting and a permit in the GTA. Composite typically adds 40% to 60% over pressure-treated for a complete deck, so the material choice alone can move a quote by thousands.

Measure the job before you price it

Price the deck you are actually building, not the one the customer described on the phone. Measure it yourself, and write down everything that changes the price.

  • Size and shape. Length and width, plus any bump-outs, angles or multi-level sections. A deck with two levels costs more per square foot than a rectangle, because every edge is framing and finishing.
  • Height above grade. A deck more than 24 inches (0.6 metres) above grade generally needs a building permit in Ontario, and a high deck needs taller posts, bracing and stairs, which all cost more.
  • Stairs and railings. Count the steps, the railing length and the gates. Stairs are the most expensive part per square foot of any deck, and they are the part most often left out of a quote.
  • Site access. Can a truck get to the backyard, or is everything carried through the house? Bad access adds labour hours on every load of lumber.
  • The old deck. Removal and disposal of an existing deck is a separate line item, not a favour. Price it, or the customer will assume it is included.
  • Ground conditions. Footings in clay, rock or a wet yard take longer and cost more than footings in clean soil.

Take photos of all of it. The photos protect you when the customer asks why the quote is higher than the neighbour’s, and they are the record you need if the scope changes halfway through.

Materials: the biggest price lever

Materials are roughly half the cost of a deck build, and the material choice is the conversation to have with the customer first, because it sets the budget for everything else.

Pressure-treated lumber is the cheapest deck material, at $35 to $60 a square foot installed on most Ontario guides, and $45 to $65 on others. It is strong, available everywhere, and easy to work with. The trade-off is maintenance: it needs sealing, it checks and warps over time, and it will not look new for long. It suits budget builds, rental properties and simple decks.

Cedar runs $55 to $105 a square foot installed. It looks better than pressure-treated and smells better too, but it needs regular sealing and it is softer, so it dents and scratches. It suits a customer who wants a natural look and accepts the upkeep.

Composite, such as Trex Select, runs $65 to $95 a square foot installed for a mid-range board. It costs 40% to 60% more than pressure-treated for a complete deck, and it earns it back in maintenance: no sealing, no splinters, no rot, and it looks the same in year ten as in year one. Most family decks in Ontario are composite now, and most customers who can afford it choose it.

PVC and capped polymer run $80 to $130 a square foot installed, and premium capped composite in the GTA runs $90 to $160. These are for wet areas, pool decks and premium builds, where the customer is paying for the best finish and the longest life.

Do not forget the parts that are not boards. Footings, posts, beams, joists, hangers, screws, flashing, railing and stairs are all materials too, and on a high deck they can be a third of the material bill. Price the structure separately from the decking, so the customer sees where the money goes. The construction material calculator helps with the quantities.

Labour: what to charge for the build

Labour is 40% to 60% of the total cost of a deck build. On a per-foot basis, labour generally runs $25 to $50 a square foot, and $40 to $70 a square foot in Toronto and Vancouver, where wages and the cost of doing business are higher. A freelance carpenter doing basic framing and decking may charge $15 to $30 a square foot for labour alone, but that is not a complete installed price.

Work out your labour from your real costs, not from a rule of thumb. Add up the crew’s wages, including burden, the days the job will take, and the time for the permit, the inspections, the deliveries and the cleanup. Then add your overhead: truck, tools, insurance, WSIB, and the office time to quote and invoice the job. A deck that takes three days with two carpenters is not a three-day job, it is a three-day job plus a day of quoting, ordering, inspecting and invoicing.

Price the whole job, not the build days

A deck that takes three days to build takes five days of your business: quoting, ordering, permits, inspections, invoicing and follow-up. If you only price the build days, the other two days come out of your margin.

Charge for the crew you actually send. A two-person crew that finishes in four days costs the same in wages as a four-person crew that finishes in two, but the four-person crew needs a bigger truck, more tools and more supervision. Price the job, not the day rate.

Permits and extras people forget

In Ontario, a deck more than 24 inches above grade, or attached to the house, generally needs a building permit. Most GTA municipalities charge $150 to $600 for a deck permit, and Toronto typically charges $250 to $450. Check with the local building department before you quote, because the permit is the customer’s cost, not yours, and it should be a line item, not a surprise.

  • Permit and inspections. The permit fee, plus the time to draw the plan, submit it and meet the inspector. Budget half a day.
  • Disposal. Removing and disposing of an old deck, including the dump fee. Price it by the load.
  • Lighting and extras. Post lights, stair lights, built-in seating, planters, privacy screens and under-deck drainage. Each one is a line item with a price, not a favour.
  • Landscaping repair. The yard will not look the same after a deck build. Budget for sod, grading and cleanup, or agree in writing that it is the customer’s job.
  • HST. In Ontario, HST applies to the job, and it should be shown separately on the quote, not buried in the total.

Put the permit in the quote as its own line, with the fee and the note that it is charged at cost. Customers accept a permit fee they can see. They do not accept a permit fee that appears after the job is signed.

Two worked examples

These are worked examples from Ontario guides, not quotes for a specific job. Your numbers will differ by town, site and material brand.

Example 1: a 12 by 16 foot deck, 192 square feet, pressure-treated. At $35 to $65 a square foot installed, the total runs $8,600 to $12,500, including footings, framing and standard railing. Materials are roughly half, labour roughly half, and the permit adds $150 to $600 on top. A simple ground-level deck with easy access lands near the low end. A high deck with stairs and a permit lands near the high end.

Example 2: a 200 square foot deck, composite. Pressure-treated would run $8,000 to $16,000. The same deck in mid-range composite runs $14,000 to $22,000, including the same footings, framing and railing. The composite premium is $6,000 or so on a deck this size, and it is the number to show the customer when they ask why composite costs more: no sealing, no splinters, and a deck that looks new in year ten.

DeckPressure-treatedComposite
12 x 16 ft (192 sq ft)$8,600 to $12,500$12,500 to $18,200
200 sq ft$8,000 to $16,000$14,000 to $22,000
Cost per sq ft$35 to $65$65 to $95
MaintenanceSeal every 1 to 2 yearsWash only
Permit (GTA)$150 to $600$150 to $600

Show the customer both columns. Most customers who see the two prices side by side choose composite, and the ones who choose pressure-treated do it knowingly, which means fewer arguments later.

A pricing formula you can reuse

Price every deck the same way, and the quotes get faster and more accurate with every job.

1. Measure
Length, width, height, stairs, railing and site access.

Write it down and photograph it.

2. Materials
Decking, structure, footings, hardware, railing and stairs.

Get a real lumber quote, not a guess.

3. Labour
Crew days, including quoting, permits, inspections and cleanup.

Price the whole job, not the build days.

4. Permit and disposal
Permit fee, old deck removal, dump fees.

Line items, charged at cost.

5. Margin
Add your margin to the total cost, not to the materials alone.

A deck is a business, not a favour.

6. Present options
Good, better, best: pressure-treated, cedar, composite.

Let the customer choose their budget.

Present the quote as options, not as one number. A pressure-treated price, a cedar price and a composite price, side by side, with the maintenance difference spelled out, turns a price objection into a choice. The customer picks their budget instead of shopping you against the next contractor. Our roofing estimate guide uses the same options method, and the quoting tools in Contruva build the options into the estimate automatically.

Mistakes that eat your margin

Most deck jobs that lose money lose it in the same five places. Check for them before you sign the quote.

  • Forgetting the stairs. Stairs are the most expensive part per square foot of any deck. Count the steps, price them, and put them on the quote.
  • Forgetting the permit. A deck that needs a permit and does not have one stops the job, and the delay costs more than the fee.
  • Pricing materials from memory. Lumber prices move. Get a quote from the yard for every job, and date it.
  • Not charging for the old deck. Removal and disposal is real work with a real dump fee. If it is not on the quote, you are doing it for free.
  • One price, no options. A single number invites the customer to compare it with the next contractor’s single number. Options invite them to choose.

Price the deck in front of the customer, line by line, and let them watch the numbers add up. A customer who has seen the materials, the labour, the permit and the options does not argue about the total, because they built it with you. And when the job is done, send the invoice the same day, with a deposit taken at signing: our getting paid faster guide covers the follow-up that closes the loop.

Sources

01Questions

Straight answers.

Still unsure? Call us at +1 (647) 922-5436. A real person picks up.

Ask us anything

How much does it cost to build a deck in Ontario?

In 2026, a deck in Ontario typically costs $45 to $95 a square foot installed. Pressure-treated runs $35 to $65 a square foot, mid-range composite $65 to $95, and premium composite in the GTA $90 to $160. A 12 by 16 foot pressure-treated deck runs about $8,600 to $12,500.

How much more does a composite deck cost than wood?

Composite typically adds 40% to 60% over pressure-treated for a complete deck. A 200 square foot deck runs $8,000 to $16,000 in pressure-treated and $14,000 to $22,000 in mid-range composite. Composite needs no sealing and looks new far longer.

Do I need a permit to build a deck in Ontario?

Generally yes, if the deck is more than 24 inches (0.6 metres) above grade or attached to the house. Most GTA municipalities charge $150 to $600 for a deck permit, and Toronto typically $250 to $450. Confirm with your local building department.

How much is labour for a deck build?

Labour is 40% to 60% of the total cost. Labour alone generally runs $25 to $50 a square foot, and $40 to $70 in Toronto and Vancouver. Price the whole job, including quoting, permits, inspections and cleanup, not just the build days.

What is the formula for pricing a deck?

Measure the deck, price materials from a real lumber quote, price labour for the whole job including permits and cleanup, add the permit and disposal as line items, add your margin to the total cost, and present good, better and best options so the customer chooses their budget.

What mistakes make deck jobs lose money?

Forgetting the stairs, forgetting the permit, pricing lumber from memory instead of a current yard quote, not charging for old deck removal, and giving one price with no options. Each one is avoidable if the quote is built line by line.