To price a bathroom renovation, start with the scope, then price labour, materials, fixtures and subtrades line by line, add overhead and profit, and finish with allowances for the things the customer has not picked yet and a contingency for what you find behind the walls. A mid-range full bathroom in Canada typically costs $15,000 to $30,000, according to 2026 Canadian cost guides, and the method below is how you get from that range to a number you can stand behind.
Bathrooms are the hardest room to price well. They are small, so every trade is in the same few square metres, and they hide the most surprises: rotten subfloor, old wiring, cast iron drains and plumbing in the wrong place. This guide gives you the 2026 cost ranges, the per-square-foot method, the line items, and a worked example. All prices are in Canadian dollars, before HST or GST, unless it says otherwise. This is general pricing information, not tax advice; check the CRA for how tax applies to your invoices.
What does a bathroom renovation cost in 2026?
Canadian cost guides for 2026 broadly agree on the ranges, even if the exact averages differ. HomeStars puts the average bathroom renovation in Canada at about $14,500, with most homeowners spending between $8,500 and $21,000. RenovationFind puts the average at $18,000, with a low end around $6,000 and a high end above $40,000. The gap between sources is the point: the range is wide because the scope is everything.
| Scope | Typical cost in Canada, 2026 | What it includes |
|---|---|---|
| Cosmetic refresh | $5,000 – $12,000 | New vanity, toilet, faucet, paint, mid-range tile floor. No layout changes. |
| Mid-range full renovation | $15,000 – $30,000 | New tub or shower, tiled wet area, quartz vanity, new lighting and exhaust, new flooring. |
| Full gut, layout moved | $28,000 – $55,000 | Moved plumbing, new drywall, custom tile shower, glass enclosure, heated floors, premium fixtures. |
| Luxury or primary ensuite | $55,000 – $120,000+ | Freestanding tub, curbless shower, double vanity, smart toilet, marble or large-format porcelain, custom millwork. |
Per square foot, a standard 40 sq ft main bathroom runs about $350 to $650 a square foot, according to RenovationFind. Labour is often 40% to 50% of the total, and licensed plumbers and electricians typically charge about $75 to $150 an hour. Use those figures as a sanity check on your own number, not as the number itself. Your price comes from your own costs, which is what the rest of this guide builds.
Price by scope first
Before you measure anything, pin down the scope in writing with the customer. A bathroom price without a scope is a guess, and guesses are where disputes start. Walk the room together and agree on:
- Layout: same layout, or is anything moving? Moving a toilet or shower drain is the single biggest cost jump in a bathroom job.
- What stays: tub, vanity, toilet, tile, mirror, lighting. Everything that stays is a line you do not price.
- Wet area: tub with a shower over it, a walk-in shower, or a curbless shower. A curbless shower costs more in waterproofing and floor work.
- Fixtures and finishes: brand and model, or an allowance. Never price a fixture you have not seen.
- Tile: floor, shower walls, feature wall, and the tile size. Large-format tile costs more to install than standard tile.
- Extras: heated floors, a steam shower, a smart toilet, a double vanity, custom millwork, a skylight.
Write it down and have the customer sign it with the estimate. If the scope changes later, it becomes a change order, not an argument. Our guide on how to handle a change order covers that process.
What drives the price up or down
Five things move a bathroom price more than anything else. Price them explicitly, or they will eat your margin quietly.
| Driver | Why it matters | Typical effect |
|---|---|---|
| Moving plumbing | New drains, venting and water lines, often through joists or concrete | HomeStars estimates $2,000 to $5,000 or more in Toronto |
| Old house surprises | Rotten subfloor, knob-and-tube wiring, lead solder, cast iron drains | A 10% to 15% contingency, see below |
| Tile and stone | Large-format and natural stone cost more to buy and install | Tile labour roughly doubles from standard to large-format |
| Waterproofing | Membrane systems, niches, curbless entries and bench seats | A few hundred to a few thousand dollars |
| Location | Labour in Vancouver and Toronto runs well above smaller centres | RenovationFind notes labour often 30% or more above the national average in those cities |
Condos add their own costs: elevator bookings, protection for common areas, restricted work hours, and board approvals. Price a condo bathroom with a site visit and a read of the building rules, not from a photo.
The pricing method, step by step
Price a bathroom the same way every time, and the number stops depending on your mood on the day you quoted it.
Measure the room, note the ceiling height, and list every scope item from demolition to the last tube of silicone.
Labour at your loaded rate, materials at supplier prices, subtrades at their quotes, permits and disposal.
A dollar figure for every fixture and finish the customer has not picked yet, with the allowance stated on the estimate.
Your overhead rate on top of direct costs. If you do not know yours, work it out from last year’s books.
A planned margin, not whatever is left over. Many contractors aim for 10% net or more.
10% to 15% for older homes, shown as its own line or built into the price.
Charge HST or GST on the full price of the job, materials and labour included, if you are registered.
The difference between markup and margin trips up a lot of contractors. Markup is a percentage of your cost; margin is a percentage of your price. A 20% markup on a $10,000 job gives you a $12,000 price and only a 16.7% margin. To hit a 20% margin you need $12,500. Our guide to pricing a contractor job walks through the difference with a worked example, and the free contractor markup calculator does the conversion both ways.
Pricing labour
Labour is usually the biggest line in a bathroom renovation, and the easiest to underprice, because the work is fiddly and slow. A bathroom is small, so trades trip over each other, and a lot of the work is in the details: tile cuts, grout lines, silicone, trim.
Price labour by trade and by day, not as one lump. Get quotes from your plumber and electrician for the job, and price your own crew’s time at the loaded rate, not the wage. A $35 an hour carpenter costs you more than $35 an hour once you add vacation pay, CPP and EI, workers’ comp and benefits, often 20% to 35% on top.
| Trade | Typical work on a mid-range bathroom | How to price it |
|---|---|---|
| Demolition and disposal | Gut to studs, remove tub, tile and vanity, bin | Half to one day plus bin and tipping fees |
| Plumbing | Rough-in, fixtures, shower valve, toilet and vanity hook-up | Subtrade quote; $75 to $150 an hour if hourly |
| Electrical | Pot lights, exhaust fan, heated floor, GFCI, mirror light | Subtrade quote; $75 to $150 an hour if hourly |
| Tile | Floor, shower walls, niche, grout and silicone | Per square foot, plus a day rate for small or fiddly areas |
| Carpentry and drywall | Subfloor repair, drywall, trim, vanity install | Loaded day rate from your own records |
| Painting | Ceiling and walls, two coats | Half a day to a day |
Track your crew’s actual hours per bathroom against the estimate. After five or six jobs you will know your real production rate, and your prices will stop being guesses. If you want the method in full, contractor job costing explains how to track estimate against actual while the job runs.
Pricing materials and fixtures
Price materials from current supplier prices, not from memory and not from the last job. Tile, fixtures and lumber prices move, and a quote that is two months old can be wrong by enough to erase the margin.
| Item | What to include | Notes |
|---|---|---|
| Tile | Floor, shower walls, feature wall, grout, adhesive, trim | Add 10% to 15% waste for cuts; more for diagonal or large-format |
| Waterproofing | Membrane, corners, pipe seals, niche, drain | Do not skimp here; a leak costs more than the membrane ever will |
| Shower and tub | Base or tub, door or curtain, valve, shower head, drain | Price the valve and trim as one set |
| Vanity and countertop | Cabinet, top, basin, faucet, mirror | Quartz costs more than laminate; state which one |
| Toilet | Unit, seat, supply line, wax ring | Check the rough-in measurement before you order |
| Lighting and exhaust | Pot lights, vanity light, fan, switches, GFCI | A quiet, properly sized fan is worth the extra money |
| Plumbing and electrical rough-in | Pipe, wire, boxes, fittings, drains | Priced from the subtrade quote |
| Drywall, paint, trim | Moisture-resistant board, paint, baseboards, caulk | Use bathroom-rated paint |
Price materials on their pre-tax cost. If you are registered for GST/HST, you claim the tax you paid on materials back as an input tax credit, so marking up the tax-included price and then charging HST again overprices the job. See do contractors charge HST on materials for the full explanation.
Allowances, not guesses
Customers rarely pick every fixture before you quote. The answer is an allowance: a dollar figure on the estimate for each unpicked item, with a clear rule for what happens when they pick something pricier.
“Tile allowance: $1,200 for floor and shower wall tile, supplied. If you choose tile above that amount, the difference is added to the final invoice at cost, plus HST.”
Give an allowance for tile, fixtures, lighting, the vanity and the mirror at minimum. State the allowance on the estimate, and state that the customer pays the difference if they go over. An allowance is not a guess; it is a budget the customer agreed to. When they pick the $900 faucet instead of the $300 one, nobody is surprised.
The hidden costs and contingency
Every older bathroom hides something. The question is not whether you will find it, it is whether you priced for it.
- Rotten subfloor. Leaks around the tub and toilet rot the floor underneath. Price a per-sheet replacement rate on the estimate, with photos, the way roofers do for decking.
- Old wiring. Knob-and-tube, ungrounded circuits and overloaded panels show up once the walls are open. Your electrician should flag the risk on the site visit.
- Cast iron and lead drains. Old drains crack when disturbed, and lead solder shows up in pre-1980s plumbing. Budget for replacement, not repair.
- Out-of-square walls. Old bathrooms are rarely square, and tile shows it. Allow extra tile labour on a fiddly room.
- Asbestos. In homes built before the mid-1980s, old vinyl tile, mastic and drywall compound can contain asbestos. If you suspect it, stop and get it tested before you demolish.
A 10% to 15% contingency is standard on older Canadian homes, according to 2026 renovation guides. Show it as its own line so the customer understands what it is for, and tell them what happens to it if you do not use it: it comes off the final invoice, or it stays as a credit. Either way, agree on it before you start.
Worked example: a mid-range 40 sq ft bathroom
Here is a full price built the way described above. All figures are illustrative, to show the method, not market rates. Plug in your own supplier prices, crew costs and margin. The bathroom is a 5 × 8 ft main bathroom, same layout, tub replaced with a walk-in shower, quartz vanity, new toilet and tile floor.
| Line item | Cost |
|---|---|
| Demolition and disposal | $1,200 |
| Plumbing rough-in and fixtures | $3,800 |
| Electrical: pot lights, fan, heated floor | $2,400 |
| Tile labour and materials | $4,500 |
| Waterproofing system | $900 |
| Shower: base, glass, valve and head | $2,600 |
| Vanity, quartz top, faucet and mirror | $2,200 |
| Toilet | $450 |
| Drywall, paint and trim | $1,100 |
| Direct costs | $19,150 |
| Overhead at 15% of direct costs | $2,873 |
| Break-even | $22,023 |
| Profit at a 10% net margin ($22,023 ÷ 0.90) | $2,447 |
| Price before tax | $24,470 |
| Contingency at 10% (older home) | $2,447 |
| Total with contingency | $26,917 |
That lands at about $610 a square foot before tax, which sits inside the $350 to $650 a square foot range Canadian guides cite for a standard main bathroom. If your number lands far outside that range, check your inputs before you send it: either you missed something, or you are pricing a different scope than the customer is imagining. Add the tax that applies where you work on the invoice.
Presenting the price
How you present a bathroom price matters as much as the number. A single lump sum invites a yes-or-no decision and a comparison with the cheapest quote. A clear, itemized price invites a conversation about what is included.
- Show the sections. Demolition, plumbing, electrical, tile, fixtures, finishing. The customer can see where the money goes.
- Give two or three options. Good, better, best: same layout with different fixtures and finishes. Plenty of customers pick the middle, and you stop competing on the cheapest number.
- State the allowances. Every unpicked item gets a dollar figure on the page.
- State the exclusions. Painting beyond the bathroom, moving plumbing, structural work, asbestos abatement, permits if not included.
- Put an expiry on it. Thirty days is common. Material prices move, and an expiry protects you while encouraging a decision.
- Make it easy to sign. A link they can open on their phone, approve and pay a deposit on beats a PDF they have to print.
For the general template behind this, use our contractor estimate template. For roofing-specific numbers, see how to write a roofing estimate and how to price a roofing job per square.
Pricing mistakes that lose money
- Pricing from memory. Supplier prices move. Check them on every quote.
- Forgetting the loaded labour rate. Costing a carpenter at the wage instead of the loaded rate quietly gives away 20% to 35%.
- No allowance rules. A customer who picks the $900 faucet without a rule in place expects you to absorb it.
- No contingency on an old house. The subfloor is rotten more often than it is fine. Price for it.
- Marking up the tax-included price. Price materials pre-tax and charge HST on the selling price, not on top of tax you already paid.
- One lump sum, no sections. The customer cannot see what they are paying for, so they shop on price alone.
- Forgetting the follow-up. A bathroom is a big decision and most homeowners collect two or three quotes. The first clear, itemized estimate that arrives has a real advantage.
Contruva’s quoting software keeps your price book for bathroom work saved, so a vanity, a shower valve and a day of tile labour are line items you pick, not numbers you retype. The customer signs on their phone and pays the deposit before you order materials, and follow-ups go out on schedule. See what else is included on the pricing page, or read how to write a contractor estimate that wins the job.
Sources
- HomeStars: Bathroom Renovation Cost in Canada, 2026: Average bathroom renovation cost of about $14,500, most jobs $8,500 to $21,000, and labour of $75 to $150 an hour.
- RenovationFind: Bathroom Renovation Cost in Canada, 2026: Average bathroom renovation cost of $18,000, $350 to $650 per square foot for a standard 40 sq ft bathroom, and labour at 40% to 50% of the total.
- CRA: GST/HST for businesses: How businesses charge, remit and report GST/HST.